POWER TRANSFORMER INSTALLATION 

A SCHEDULED CONSTRUCTION PROJECT

    The transformer is a static equipment, amongst most efficient electrical equipment which converts High Voltage to Low voltage or vice versa and shall be at any desired power capacity. Power transformer normally used in transmission system purposes for high-capacity power transformation usually installed in substations. The capacity of Power transformer indicates in MVA and when it increases, the physical properties like dimension, oil capacity, height, weight and protection system complexity, transportation, maintenance, etc increases. Similarly, the erection process or installation time also increases. In my piece of writing, I am trying to describe the installation of POWER TRANSFORMER of capacity above 20 MVA that to be conducted as a construction project with time schedule. 

      When the design, project drawings, submittals and equipment manufacturer were chosen as approved by the end user, the equipment manufacturer start to manufacture, getting ready for FAT (factory Acceptance Testing) so as to start shipping to the designated project site. After confirming the shipment order, the manufacturer of Power transformer will ship their product to the project site as multiple part packages including oil conservator, incomer bushings, outgoing cable terminal boxes, tap changing assembly, indicating meters, protection system, neutral grounding system etc. in addition to main core Tank.

      These part packages will arrive to project site one by one in separate shipment containers and among these, the most weighed part is transformer main core Tank and shall be up to 450 tons. Containers arrive in separate transit trucks or consignment. As soon as arrive at the site, it has to be inspected by a qualified Quality Engineer (QA/QC Engineer). The manufacturer of the power transformer will attach the checklist of contents in the particular shipment and this is to be verified by the concerned inspector. If any damage or discrepancy noted in the shipment as per checklist, check impact recorder readings any, check the graph and the information to be immediately passed over to manufacturer through the desired format attached along with the shipment package checklist.

      Here we go as the total process of the installation of high capacity power transformer considered as an INSTALLATION PROJECT.

           The total time of project shall be for a period up to six months or can be lesser, if well planned. Each activity in the project shall be named as Task and can be linked to project/construction software like “MS Project” or similar. Through these type of project software, the erection, assembly, testing, pre-commissioning, commissioning and handing over shall be monitored, updated and completed in a scheduled manner without omitting every minute task. So that the installation of a power transformer can complete and switch on to service within stipulated schedule. The power transformer associated equipment like CT, VT, NGR, SCADA, Switch gears, air/water Cooling system, Fire fighting and Alarm system etc also to be planned most suitable to complete the total installation project within the scheduled time. 

   

 

 

 

 

 

 

 

 

THE MAIN TRANSFORMER TANK ARRIVES TO SITE

      It may have to collect the Transformer Main Tank from seaport to the project site by special expert Transporting/Logistic companies. Transportation is an important task element when concerned with the total nature of the project as it weighs as much as 450 tons and often requires long-distance transport.The following manpower is usually utilized in the transformer installation and to be included in schedule preparation.

  1. Project Manager.
  2. Project Engineer and Supervisors.
  3. Inspection Engineer or Supervisor. 
  4. Commissioning Engineer.
  5. Safety Supervisors.
  6. Skilled Technicians such as electricians, fitter, welder, crane operators, riggers, labours, etc.
  7. Third-party testing agency for pre-commissioning, testing and commissioning jobs

   The following activities considered as Tasks in Project Software, which may plan and scheduled in a pro-active manner.

  1. Completion of transformer civil foundation/plinth, oil drain pit, transformer fencing parapet, earth pit, etc.
  2. Approval of Project drawing including area dimensions, specifications and submittals.
  3. Approval of transformer specifications, selection of manufacturer.
  4. Mobilization of specified manpower required.
  5. Receive of Transformer main Tank and accessories at the project site and unloading at the temporary storage area.
  6. Logistics of Transformer Main tank from seaport to the project site.
  7. Unboxing accessory pieces of equipment listed as received.
  8. Inspecting the received equipment whether in good condition and listed.
  9. Arranging Cranes forklift, loader and trucks as per required weight specifications of the equipment.
  10. Transporting transformer tank unit and accessory equipment to the desired foundation/location from the temporarily stored area.
  11. Installation and rigging work of main transformer tank unit.
  12. Assembly of medium weighed parts like Cooling Fins, Forced oil cooling pumps, Forced Air Cooling Fan, Forced water-cooling system, water cooling tower, etc.
  13. Erection of Primary high voltage Terminal Bushings.
  14. Erection of Conservator Tank 
  15. Tap changer assembly, indication and protection relays.
  16. Installation of Indication instruments like Winding temp., Oil temp, oil level, Nitrogen Gas pressure gauge, etc.
  17. Installation of breather and breathing analyzer.
  18. Selection and arranging third party inspection team as per requirement
  19. Arranging required capacity of Temporary 3 phase power supply at the project site.
  20. Arranging secondary terminal connections and NGR System
  21. Procuring transformer insulation oil as per time capacity
  22. Arranging oil filter plant for monitoring the insulation oil properties 
  23. Oil is to send to the accredited laboratory to verify physical and chemical properties, BDV, dissolved gas analysis, etc)
  24. Transformer oil filling process.

(Manufacturers will not fill the transformer oil in the main tank of large three-phase three-limb power transformer during transit but it can be arranged locally as per the convenience of the project manager if required.)

  1. Main Tank vacuuming process.
  2. Nitrogen filling process in tank if recommended by the manufacturer.
  3. Pre-commissioning tests like ratio, polarity, vector group, no-load losses, OC, SC Tests, percentage impedance, winding and insulation tests.
  4. Pre-commissioning tests of protective relays, oil level meters, Buchholz relay, indications, alarms etc
  5. Inspection and Testing OLTC and its operation including limit switches. 
  6. Tan-Delta moisture content tests/capacitance tests, etc.
  7. Commissioning Tests like the functioning of OC/EF, differential relays, Buchholz relay, REF or other tests. SAT (Site Acceptance Test) in addition to the above commissioning tests of the associated CT, VT, Switch Gear also to be completed. 
  8.  Vendor or manufacturer of the associated equipment shall be other than the transformer unit manufacturer. Therefore, a time-dependent coordination process has to do during the commissioning stage to coordinate with the complete vendor team. Moreover, the interconnection between switchgear, transformer, associated equipment, and the protective system has to do in a scheduled manner during pre-commissioning. 
  9. Hotel accommodation/gate passes of the vendor engineers or subcontractors arriving for commissioning distant/other than homeland to be arranged conveniently and suitably as profit-oriented. The equipment gate passes for crane, Front-end loader and special transformer logistic companies and Man Gate pass of the equipment operating staff, vendor/supplier engineers also to be arranged with local agencies like municipality, other utility companies, police, telecom, etc to be concerned in high priority during the execution of the project peak time.

   The total installation time shall be six months or more depending upon the size of the power transformer and may split as follows.  Material receiving, unboxing, material inspection at the site -up to two to three months.

  •    Installation of the transformer and its accessory equipment -up to one month.
  •   Pre-commissioning tests -up to one month.
  •    Commissioning and Co-ordination process. -up to two months.
  •    Documentation, Dossier Preparation and handing over -10 days

   The project tasks specified shall be further divided into several minor/micro tasks and the period shall be limited precisely before project completion. After verifying each task, the project schedule shall verify further to compress the time requirement if possible.

      In short, the High MVA capacity power transformer installation process has to be considered as a scheduled project and it is not so simple as all the above process of completion is involved. If we can plan accurately and schedule every specified task, the project can be completed well before time and will be appreciated well by the end-user.

(Written By - Er. JOHN VARGHESE, Proprietor, JAITECH ENGINEERS, Mob No : +91 99950 67144)

 

 

Free Website Created & Hosted with Website.com Website Builder

Create Yours

Create Free Website Now

Stunning Website Templates. Free Domain.
website.com: Get Your .COM Domain for Just $14.77/year No Hidden Fees Register Now