In a substation or powerhouse there will be control room where the operator wants know the position and status of equipment as ether it working, open or close. Now a days everything can be viewd or controlled from control room HMI computer, it is better to know what is Mimic Diagram. The mimic diagram provides the operator with an overview of the status of the power system. In the power house there will be higher number of equipment connected together and will be working or not according to the logic designed. Therefore, there can draw line, usually red in color on the panel starting from initial stage equipment and the line end till the output stage.
It is a combination of static as well as dynamic indications. The static indication shows devices such as transmission lines, bus-bars and transformers where as the dynamic indication shows the current state of the devices such as breakers, isolators, valves, etc.
The MIMIC line diagram and Single Line Diagram are similar. MLD may draw on the surface of equipment control panel but SLD be on white Paper as foldable can keep in safe custody for any reference. The SLD designed through computer software where as MLD is the quick reference in front of the operator to view the status of equipment,which usually printed on the panel surface.
In a control room all the field equipment like switch gear, motor, valves are away from control room, but the status of the equipment will indicate in the line provided as small glowing colored or mimicked with an illuminated LED in red, green or yellow. So the operator in charge of the shift will identify whether the equipment working, tripped or stop. It is an easy way than to inspect and identify the condition of equipment than to check locally.
Nowadays the MIMIC diagram incorporated in the HMI or operators computer screen as all the control activities are through SCADA. The mimic diagram can also accommodate analog meters, digital displays, directional power flow indicators and chart recorders. Therefore, MLD is an integral part of SCADA. If the control room operator want to switch-on the breaker or he want to operate a valve to a particular percentage, which is possible through MLD of his computer screen.